Regulatory watch
Data center moratoriums, zoning changes, and utility and power policy that affect project timing. The list carries over week to week and changes only when something changes.
As of November 16, 2026
Florida
Florida (statewide), FLUpdated this week
The Public Service Commission unanimously rejected Duke Energy Florida's large-load cost proposal as not meeting Senate Bill 484.
Source. Effective Jul 1
Georgia
Cobb County, GA
Moratorium on new applications and permits runs to at least early February 2027.
Dade County, GAUpdated this week
A 90-day pause was reported approved Nov. 5. A second report says the ordinance went back to a county board, so its status is unconfirmed.
Lee County, GAUpdated this week
Moratorium in unincorporated areas extended to the end of June 2027.
Source. Expires June 30, 2027
Paulding County, GA
Moratorium on new data centers runs through Jan. 1, 2027.
Source. Expires January 1, 2027
Alabama
Trinity, ALUpdated this week
Town moratorium runs until June 2027. A 184-acre rezoning request was withdrawn this month.
Tennessee
Knoxville, TN
One-year city moratorium runs to July 7, 2027, or until new rules take effect.
Source. Effective Jul 7. Expires July 7, 2027
Memphis, TNUpdated this week
A 135-day pause on approvals began Oct. 20. On Nov. 10 the council asked for recommended standards within 60 days.
Source. Effective Oct 20